On 13 November 2026, the Grand Aquarium de Saint-Malo unveiled a new version of its extension project. Now refocused solely on the plot already owned by the aquarium, it no longer encroaches on the neighbouring 775 m² copse, whose planned sale had triggered legal action and petitions. The rest of the project remains unchanged.

The 775 m² copse spared after all

This is the change that has shifted the balance. In this second version, the project focuses solely on the land the aquarium already owns. The 775 m² wooded plot, whose sale the town council had voted through on 2 July 2026, is no longer part of the plans. This small copse, which local residents described as a green lung and a cool-air refuge, had united the opposition. The aquarium now says its plan has secured agreement from all parties involved.

Residents' campaign pays off

Local residents hadn't let up. The Flourie - Malo Plein Sud association had lodged an appeal with the administrative court on 3 September 2026 against the sale of the land. Two petitions had circulated, one led by a tree-protection group with more than 3,300 signatures, the other gathering almost 600 local residents. A rally had been held in mid-October.

"Common sense won out in the end."

The committee remains watchful, however, and is calling for this green corridor to be permanently protected.

What the extension still includes

The core of the project remains unchanged. The aquarium plans to create a large basin holding 3,300 m³ of seawater, home to sharks and rays, crossed by a tunnel and lined with wide glass walls. Around twenty hotel rooms overlooking the basin and a restaurant are also planned. The stated aim is to extend the average visit by about thirty minutes, boost visitor numbers by roughly 10%, and spread attendance more evenly across the year, given the site already welcomes 400,000 visitors. The extension is also expected to create around forty jobs.

Planning application expected by the end of the year

The next step is now in the hands of the authorities. The aquarium, owned by the Looping group, plans to submit its new version before the end of 2026. Its director, Philippe Vignaud, is championing a facility that, thirty years after opening, he says needs fresh momentum. The original project was estimated at €34 million. The town council backs the scheme and is awaiting the outcome of the public inquiry. The extension is still targeted to open around 2029.

Visiting the aquarium and the surrounding area

In the meantime, the Grand Aquarium de Saint-Malo and its submarine remain open, as does the Tropical Freshwater Aquarium in the corsair city. For an outdoor outing further inland, Cobac Parc in Lanhelin makes an easy addition to a weekend in Saint-Malo. Plenty to keep you going while you wait for the public inquiry's verdict.

Your questions, our answers

What does the new version of the project change?

The extension is now refocused solely on the plot the aquarium already owns. The neighbouring 775 m² copse, whose sale was approved in July 2026, is no longer affected. The rest of the project remains unchanged: a large 3,300 m³ basin, a hotel with around twenty rooms and a restaurant.

Continues after this ad

Why were local residents opposed to the project?

The first version involved building on a 775 m² copse, seen as a green lung for the neighbourhood. Residents raised concerns about soil sealing, nuisance and a lack of transparency. An association lodged an appeal with the administrative court, and two petitions gathered several thousand signatures between them.

When might the extension open?

The aquarium plans to submit its new version before the end of 2026, ahead of a public inquiry. The extension's opening, featuring its shark and ray basin, tunnel and immersive hotel, is still targeted for around 2029, subject to approval.