Fourteen months after it was filed, the planning application for the future Puy du Fou park in England remains undecided: as of late October 2026, Cherwell District Council's planning register shows no vote on case 25/02232/OUT. The project covers 150 hectares north of the village of Bucknell, three kilometres from Bicester (Oxfordshire), with €700 million to be invested over ten years.

Live performance, not roller coasters

The British application follows the same recipe as Les Epesses in the Vendée: actors, horses, and not a single mechanical ride on the programme. Four period villages, thirteen shows (six outdoors, seven indoors) spanning everything from Roman occupation to the Second World War, three themed hotels and a conference centre make up the plans submitted to the council.

One figure underpins the whole economic case: 1.47 million visitors a year once the park reaches full capacity, after 550,000 in the first year, according to the application documents. Everything else flows from that forecast, including around 2,000 direct jobs and €350 million committed in the very first year out of the €700 million planned.

The site, within easy reach of Junction 10 of the M40, would retain 16 hectares of meadows, with 20,000 trees planted and 5 kilometres of hedgerows. For a French theme park operator, the scale is out of the ordinary: near Caen, Festyland's expansion project is playing in an entirely different league.

Continues after this ad

Puy du Fou in England: Cherwell District Council still hasn't ruled

Filed in August 2025, the application was registered on 29 August 2025 under reference 25/02232/OUT, an administrative validity check that opens the assessment process without approving anything.

Since then, the council's planning register has recorded neither a committee hearing nor a notified decision, even though the decision target was set for 31 July 2026. The application falls under "outline" procedure, the British equivalent of an approval in principle: the council first rules on the big parameters — road access, noise, water, landscape — with detailed plans to follow via separate applications. Each technical opinion reopens a section of the file.

Prestigious backers, stubborn objections

The Royal Shakespeare Company has written to the council welcoming the project, Blenheim Palace's chief executive Dominic Hare has called for its approval, and the British performing arts union Equity has publicly backed it in the name of skilled jobs and training.

Puy du Fou has also highlighted support from the Silverstone circuit and from Universal Destinations & Experiences, whose own future park is located at Kempston Hardwick, near Bedford, around fifty kilometres further east.

According to actu.fr, partnerships are also being discussed with Activity Learning and Buckinghamshire New University, and Nicolas de Villiers describes a local economy that is "enthusiastic and impatient".

Continues after this ad

The reality on the ground tells a more nuanced story. Oxfordshire County Council's transport department maintains its objection and deems the traffic impact "severe", while the North Oxfordshire Residents Action group is calling for an independent inquiry into the cumulative effect of major developments in the area. Added to this are concerns over noise from night-time shows, access to the countryside, the loss of farmland and the welfare of animals used on stage.

An opening between 2029 and 2031, and already an eye on Italy

The application as filed describes a phased opening from 2029, running an April-to-October season. Group management, however, was talking more about 2030 or 2031 on 21 October 2026. On the same day, chief executive Olivier Strebelle confirmed another avenue: "We are currently looking for sites in Italy," with no location or timeline given. Until Cherwell convenes its planning committee, these English dates remain indicative, and the British project is stuck in administrative limbo while the Italian search, unlike it, has no planning permission to clear.